Project Name: Mitchell Expansion I
1. The building pad has been complete for the entire new addition and connecting corridor.
2. Exterior wall panels have been constructed on the ground to expedite erection.
3. All concrete footings/foundations have been completed.
4. The masonry perimeter block has been installed and fully grouted.
5. The exterior wall panels are nearly complete and ready for erection