Thursday, May 12, 2016

Mitchell Expansion Construction Report - 4-12-16

Time Period:   – April 30- May 13

Project Name:  Mitchell Expansion I

CONSTRUCTION

1.  All exterior walls have been erected.

2. All underground plumbing inside the building has been installed.

3. All underground electrical inside the building has been installed.

4. The concrete floor for the entire building has been completed.

5. Erection of the interior bearing wall has commenced and is ongoing.